Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
A steering committee will evaluate and assess all possible systems development that a firm may undertake. This committee will evaluate the feasibilities of the proposed system. Which of the answers below are NOT part of a feasibility categories?
A
operational
B
technical
C
human
D
none of the above
Explanation: 

Detailed explanation-1: -There are four main elements that go into a feasibility study: technical feasibility, financial feasibility, market feasibility (or market fit), and operational feasibility.

Detailed explanation-2: -The 5 types of feasibility study are Scheduling Feasibility, Operational Feasibility, Legal Feasibility, Economic Feasibility, and Technical Feasibility.

Detailed explanation-3: -Operational Feasibility Operational feasibility is performed to understand well a proposed system solves the problems. From this aspect, operational feasibility studies are critical for system engineering and affect early design phases.

Detailed explanation-4: -What Is the Main Objective of a Feasibility Study? A feasibility study is designed to help decision-makers determine whether or not a proposed project or investment is likely to be successful. It identifies both the known costs and the expected benefits.