FUNDAMENTALS OF COMPUTER

SYSTEMS DEVELOPMENT ANALYSIS

SYSTEMS DEVELOPMENT METHODS AND TOOLS

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following is not major categories of risk?
A
First-rate of development
B
Errors & Omissions
C
Security Breach
D
Counterfeit Act
Explanation: 

Detailed explanation-1: -There are five categories of operational risk: people risk, process risk, systems risk, external events risk, and legal and compliance risk.

Detailed explanation-2: -Explanation. Risk elimination is not a type of risk management strategies.

There is 1 question to complete.