During every project team meeting, the project manager asks each team member to describe the work he or she is doing, and the project manager assigns new activities to team members. The length of these meetings has increased because there are many different activities to assign. This could be happening for all the following reasons EXCEPT:
A
Lack of a WBS
B
Lack of a responsibility assignment matrix
C
Lack of resource leveling
D
Lack of team involvement in project planning
Explanation: 

Detailed explanation-1: -The project manager is primarily responsible for the successful completion of a project. The project manager’s role is to ensure that the project proceeds within the specified time frame and under the established budget while achieving its objectives.

Detailed explanation-2: -direct, manage and motivate the project team. develop and maintain an agreed project plan and detailed stage plans. understand and apply business case and risk management processes. tailor expert knowledge to meet specific circumstances.