ENTREPRENEURIAL OPERATIONS
PRODUCTION PLANNING AND CONTROL
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
A request created in the planning run for a material in the future (converts to either a production or purchase order)
|
Planned Order
|
|
Production Order
|
|
Purchase Order
|
|
None of the above
|
Explanation:
Detailed explanation-1: -When you trigger the conversion of the planned order from SAP APO in SAP R/3 then SAP R/3 copies the components of the planned order to the manufacturing order and explodes the routing. When the manufacturing order is saved, the system deletes the planned order in SAP R/3 and creates the manufacturing order.
Detailed explanation-2: -Planned orders are created as a result of shortage of materials that are set to internal procurement, will create planned orders and you can convert planned orders to production orders using T-Code: CO40/CO41.
There is 1 question to complete.