A request created in the planning run for a material in the future (converts to either a production or purchase order)
A
Planned Order
B
Production Order
C
Purchase Order
D
None of the above
Explanation: 

Detailed explanation-1: -When you trigger the conversion of the planned order from SAP APO in SAP R/3 then SAP R/3 copies the components of the planned order to the manufacturing order and explodes the routing. When the manufacturing order is saved, the system deletes the planned order in SAP R/3 and creates the manufacturing order.

Detailed explanation-2: -Planned orders are created as a result of shortage of materials that are set to internal procurement, will create planned orders and you can convert planned orders to production orders using T-Code: CO40/CO41.