Among the listed items below, which one is not the input required to develop the MRP?
|
Bill of material
|
|
Lead time
|
|
Routing file
|
|
Inventory data
|
Explanation:
Detailed explanation-1: -MRP Inputs MRP Information Sources: There are four key information sources that MRP systems use to make their calculations. These sources include production schedules, material specs, production cycle times and supplier lead times.
Detailed explanation-2: -Material planning and production scheduling. Production control and shop-floor reporting. Inventory management. Procurement. Sales and order fulfillment. Product costing. 02-Nov-2017