Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Determines how the debit cost elements are assigned to the settlement cost elements
A
Settlement Profile
B
Settlement Structure
C
Settlement Rule
D
None of the above
Explanation: 

Detailed explanation-1: -The allocation structure assigns the cost elements under which the actual costs are written to the general cost object to settlement cost elements. There are two possible methods: You group the debit cost elements and assign each group to one settlement cost element.

Detailed explanation-2: -Cost settlement methodology generates reimbursement for services based on both claim payments for services rendered (interim payments), and a settlement of the costs associated with the provision of services.