Formulas are entered in the work center, so that the costs of an operation can be calculated. A work center is also assigned to a cost center.
A
Scheduling Information
B
Costing
C
Capacity Planning
D
Simplifying operation maintenance
Explanation: 

Detailed explanation-1: -What is a Cost center in SAP? In SAP production planning, each work center will be assigned to one cost center. For every activity type defined in a work center, an activity rate will be maintained in the cost center. SAP system uses this information to calculate activity cost for an operation.

Detailed explanation-2: -Cost center is place where you incur your costs. Work center is a place where an operation is performed by a person/machine (group). Link between them: The activities performed at or by the work center are valuated using charge rates which are defined/determined by cost centers and activity types.

Detailed explanation-3: -A work center is a location where production activities take place. Depending on the activities, people and machines are linked to specific work centers. Work centers are maintained in the bill of critical capacities.