Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Procurement cycle time is time consumed for
A
Receiving of raw material
B
Inspection of various raw materials
C
Inspection of purchased components parts
D
All of the above
Explanation: 

Detailed explanation-1: -Production Planning and Control aims to ensure cost-efficient and timely manufacturing of goods by coordinating with multiple departments.

Detailed explanation-2: -Scheduling is related to the timetable in production planning and control activities.

Detailed explanation-3: -Answer : Routing-Scheduling-Dispatching-Follow up Routing : Routing can be defined as the process of deciding the path of…