The bill of material does not consists of
A
Part number
B
Specifications of part
C
Name of the part
D
Price of the part
Explanation: 

Detailed explanation-1: -From the above figure, we can see that it contains the Part number, Quantity, and Specifications but not the price.

Detailed explanation-2: -A bill of materials (BOM) is a comprehensive inventory of the raw materials, assemblies, subassemblies, parts and components, as well as the quantities of each needed to manufacture a product.

Detailed explanation-3: -A bill of materials (BOM) is a comprehensive list of parts, items, assemblies, subassemblies, intermediate assemblies, documents, drawings, and other materials required to create a product. The BOM can be thought of as the recipe used to create a finished product, presented in a hierarchical format.