The correct sequence of operations in production planning and control is
A
Routing-Scheduling-Dispatching-Follow up
B
Scheduling-Routing-Dispatching-Follow up
C
Dispatching-Routing-Scheduling-Follow up
D
Routing-Scheduling-Follow up-Dispatching
Explanation: 

Detailed explanation-1: -Dispatching: It is the action, doing or implementation stage. It comes after routing and scheduling.

Detailed explanation-2: -Routing-Scheduling-Dispatching-Follow up.

Detailed explanation-3: -The information on the product being manufactured. Details of each relevant operation. The set-up time. The standard time is needed to finish the production. 10-Mar-2023