ENTREPRENEURIAL OPERATIONS
TIME MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
Control schedule
|
|
Estimate Activity Durations
|
|
Estimate Activity Resources
|
|
Sequence activities
|
Detailed explanation-1: -In project time management, the main outputs of the sequencing activities process are an activity list, activity attributes, a milestone list, and project management plan updates.
Detailed explanation-2: -Activity duration estimates are approximations of how much time a project task will take. They can be in the form of different time periods, such as hours, days, weeks or months, and usually refer to work or business periods.
Detailed explanation-3: -The critical path method (CPM) is a technique that’s used by project managers to create a project schedule and estimate the total duration of a project.
Detailed explanation-4: -Schedule Management Plan. Activity List. Activity Attributes. Activity Resource Needs. Resource Calendars. Project Scope Statement. Resource Breakdown Structure. Risk Register. More items