Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Completion of the successor activity depends upon the completion of its predecessor activity.
A
start-to-start
B
start-to-finish
C
finish-to-start
D
finish-to-finish
Explanation: 

Detailed explanation-1: -Start-to-finish. The completion of the successor activity depends upon the initiation of the predecessor activity. In PDM, finish-to-start is the most commonly used type of precedence relationship.

Detailed explanation-2: -1. Finish-to-Start. The Finish-to-Start relationship means that one activity-the predecessor-must be fully complete before any following-successor-activities may begin.

Detailed explanation-3: -Finish-to-finish (FF) Indicates that the finish date of the predecessor task determines the finish date of the successor task. For example, if you have rented a lab for editing the scenes, the editing task must be complete when the lab rental ends.

Detailed explanation-4: -According to the PMBOK Guide, “Finish to Finish is a Logical Relationship in which a Successor Activity cannot finish until a Predecessor Activity has finished.” In simpler words, the end of the successor activity depends on when the predecessor is done.

Detailed explanation-5: -According to the PMBOK Guide, “Finish to Start is a Logical Relationship in which a Successor Activity cannot start until a Predecessor Activity has finished.” This is the most commonly used relationship in a network diagram; the start of the successor activity depends on the predecessor activity’s finish.