The inputs used in the Define Activities process includes all BUT
A
Scope baseline
B
Milestone List
C
EEF
D
OPA
Explanation: 

Detailed explanation-1: -An activity list is a document that includes all the scheduled activities that are part of a project. Each activity includes one or more tasks that, once completed, allows everyone working on the project to move on to the next stage. Each activity has a clearly defined start date and deadline.

Detailed explanation-2: -An activity is typically one stage of a project management plan. Each activity consists of one or more actions that, upon completion, will lead to the next project stage. Taken together as a series, the activities will result in the final deliverable.

Detailed explanation-3: -The process should be done in adequate detail to estimate the resources and time that is required to complete it. Scope baseline is the primary input, consisting of the approved project scope statement, the work breakdown structure, and the WBS dictionary.

Detailed explanation-4: -Waterfall. Waterfall is often called the “traditional” project management approach. Agile. Agile is an approach to project management that is built on small, incremental steps. Lean. Scrum. Kanban. 14-Dec-2022