Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following is the output of the Plan Schedule Management process?
A
Activity list
B
Schedule Management Plan
C
Milestone list
D
Project Schedule Network Diagram
Explanation: 

Detailed explanation-1: -The primary output of a schedule management plan is the project schedule, an essential component of a comprehensive project plan. A thorough schedule management plan is essential for project progress and success.

Detailed explanation-2: -During the Develop Schedule process, which is the 6th process of Time Management Knowledge Area, the outputs of the Time Management processes occurred before are organized and the final schedule of the project is produced. This is the key output of the Develop Schedule process.

Detailed explanation-3: -What is it? Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing and controlling the project schedule. In other words, plan schedule management process aims to ensure the timely completion of a project.

Detailed explanation-4: -Project charter is an input to the Plan Schedule Management process.

Detailed explanation-5: -What Are the Inputs? Inputs to developing the schedule management plan include the project management plan, the project charter, enterprise environmental factors and organizational process assets.