If in the screening stage of EIA, the impact level of a developmental project is not discernible, then what step should be adopted?
A
Scoping stage is to be followed.
B
A rapid EIA study is to be conducted.
C
Detail EIA study is to be conducted.
D
The project should be given Environmental Clearance.
Explanation: 

Detailed explanation-1: -If in the screening stage of EIA, the impact level of a developmental project is not discernible, then what step should be adopted? (A) Scoping stage is to be followed.

Detailed explanation-2: -Screening is the first stage of the EIA process which results in a key EIA decision, namely to either conduct the assessment (based on the likely significant impacts) or not conduct it (in the anticipated absence of such impacts).

Detailed explanation-3: -The steps foreseen include (a) Screening of the Project; (b) Preliminary Assessment of Environmental Impact; (c) Design Revision and Phased Environmental Analysis; and (d) Detailed, or Formal, Environmental Impact Assessment.

Detailed explanation-4: -Screening is that part of the EIA process which determines whether an EIA is required for a particular project. Scoping is the activity of deciding on matters to be investigated as part of the EIA, once a decision has been taken that an EIA is required (i.e. once a screening decision has been made).