Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
The longest time path through a network
|
|
The shortest time path through a network
|
|
For which earliest start time and latest start time are same
|
|
For which earliest finish time and latest finish time are same
|
Detailed explanation-1: -The critical path (or paths) is the longest path (in time) from Start to Finish; it indicates the minimum time necessary to complete the entire project.
Detailed explanation-2: -The longest path through the network is the critical path. The difference between the early end date and the required completion date of the project is the total project float, and the start date of each activity is the early start date.
Detailed explanation-3: -In project management, a critical path is the sequence of project network activities that adds up to the longest overall duration, regardless of whether that longest duration has float or not. This determines the shortest time possible to complete the project.
Detailed explanation-4: -The critical path is the longest path of the network diagram. The activities in the critical path have an effect on the deadline of the project. If an activity of this path is delayed, the project will be delayed.
Detailed explanation-5: -Answer and Explanation: EXPLAINATION: Because in the critical path, there is no slack time and the project has a starting and ending date so, it is the longest path through network.