Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
If an organization has already defined a standard for how business analysis is performed, how should the business analyst proceed with planning the business analysis approach?
A
The business analyst does nothing. The project manager will put together the milestones around the current standard tasks and will assign them to the business analyst.
B
The business analyst must consult with her/his manager and brainstorm on the most important task to perform for the particular project.
C
The business analyst must inform the team on the current standard, and let the team decide on what business analysis task will be appropriate for the project.
D
The business analyst reviews any existing organizational standards, including standards, guidelines, and processes relating to the current initiative.
Explanation: 

Detailed explanation-1: -Answer: (a) The technique you’ll use is simply problem tracking. This technique allows the business analyst to manage any issues identified within requirements by stakeholders and to ensure that those issues are resolved.

Detailed explanation-2: -Project Manager: works with the business analyst to ensure that overall project governance aligns with the business analysis governance approach. Regulator: may impose rules or regulations that need to be considered when determining the business analysis governance plan.

Detailed explanation-3: -D. The business analyst will need to make a decision on which requirement is most appropriate. One of the processes within requirements analysis is to prioritize requirements.

Detailed explanation-4: -The project manager is responsible for ensuring that the business analysis plan is compatible with the project plan.