Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
Number of Sponsors
|
|
Size of the change
|
|
Technological complexities
|
|
Geographic and cultural considerations
|
Detailed explanation-1: -9] group a number of factors that seem to contribute to the perception of project complexity under the following headings: goals, stakeholders, interfaces and interdependencies, technology, management process, work practices, and time.
Detailed explanation-2: -According to project management experts Remington and Pollack, there are four types of complexity that determine the selection of projects. These include structural, technical, temporal, and directional complexity.
Detailed explanation-3: -Good planning, diligent execution, timely and appropriate communication, and management of stakeholder expectations are all essential elements in delivering a project to completion. This simple statement belies the complexities involved in any project implementation.
Detailed explanation-4: -Project complexity is the property of a project which makes it difficult to understand, foresee, and keep under control its overall behavior, even when given reasonably complete information about the project system.