MANAGEMENT

BUISENESS MANAGEMENT

FINANCIAL MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
What is ETC?
A
Extended Time Constraints
B
Estimate to Completion
C
Estimate to Compare
D
Engage the Client
Explanation: 

Detailed explanation-1: -The Estimate To Complete (usually abbreviated ETC) is the cost performance index and project management measure that shows you the remaining cost you expect to pay in order to complete a project. Note that ETC isn’t the final overall expected project budget-this is called Estimate at Completion (EAC).

Detailed explanation-2: -Term Definition Estimated time to complete is a projection of the time and or effort required to complete a project activity. Estimated time to complete is a value that is expressed in hours of work required to complete a task or project.

Detailed explanation-3: -Estimate at completion (EAC) predicts total costs, while estimate to complete (ETC) predicts the money a project still needs. ETC is the forecast of all additional money required to complete a project. It does not account for money already spent.

Detailed explanation-4: -ETC is an abbreviation of “Estimated Time to Complete” and gives the project manager an indication of when the individual assignments on a project are projected to be finalised by the project members.

There is 1 question to complete.