MANAGEMENT

BUISENESS MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
All of the following are inputs to the Identify Risks process EXCEPT:
A
Risk management plan.
B
Scope baseline.
C
Risk mitigation plan.
D
Quality management plan.
Explanation: 

Detailed explanation-1: -Risks are found among all the other constraints on the project, so the inputs will come from the knowledge areas for scope, schedule, cost, quality, and resources.

Detailed explanation-2: -Probability and impact matrix is not used as an input to the Monitor Risks process.

Detailed explanation-3: -12. All of the following are ALWAYS inputs to the risk management process EXCEPT: Historical information.

Detailed explanation-4: -The risk register is the output of the identify risks process.

There is 1 question to complete.