BUISENESS MANAGEMENT
RISK MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
All of the following are inputs to the Identify Risks process EXCEPT:
|
Risk management plan.
|
|
Scope baseline.
|
|
Risk mitigation plan.
|
|
Quality management plan.
|
Explanation:
Detailed explanation-1: -Risks are found among all the other constraints on the project, so the inputs will come from the knowledge areas for scope, schedule, cost, quality, and resources.
Detailed explanation-2: -Probability and impact matrix is not used as an input to the Monitor Risks process.
Detailed explanation-3: -12. All of the following are ALWAYS inputs to the risk management process EXCEPT: Historical information.
Detailed explanation-4: -The risk register is the output of the identify risks process.
There is 1 question to complete.