Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following risk management activities is out of sequence in terms of timing?
A
Identify, assess, and prioritize risks.
B
Develop risk responses/treatments.
C
Determine key organizational objectives.
D
Monitor the effectiveness of risk responses / treatments.
Explanation: 

Detailed explanation-1: -5. Which of the following risk management activities is out of sequence in terms of timing? a. Identify, assess, and prioritize risks.