Which one IS NOT the part of Risk Identification:
|
Cause
|
|
Impact
|
|
Control
|
|
Loss Event
|
Explanation:
Detailed explanation-1: -Answer is “not watching for new Risk".
Detailed explanation-2: -There are five core steps within the risk identification and management process. These steps include risk identification, risk analysis, risk evaluation, risk treatment, and risk monitoring.
Detailed explanation-3: -Risk elimination is not a type of risk management strategies.