You are setting up your project team, and you are looking at a chart that shows that the programming will be performed by Systems Development, the infrastructure will be implemented by Infrastructure Systems, and the customer communication will be handled by the Call Center. This is an example of what type of chart?
A
RACI
B
Organizational Breakdown Structure (OBS)
C
Work Breakdown Structure (WBS)
D
Resource Breakdown Structure (RBS)
Explanation: 

Detailed explanation-1: -The correct answer is (C) Create a WBS. WBS allows to break a project into manageable units by all team members, each level of the WBS for deepening the details of the tasks to final level: the concrete tasks to perform .

Detailed explanation-2: -Which of the following BEST describes a project management plan? Explanation: The project management plan includes more than just a bar chart and the project manager’s plan for completing the work. It includes all the management plans for the project.