Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
A sequence of tasks that cannot be delayed without causing the project to be completed late.
A
Float
B
Critical path
C
Milestone
D
Payback period
Explanation: 

Detailed explanation-1: -What is a critical task? Tasks that cannot be delayed without affecting the project finish date are the critical tasks.

Detailed explanation-2: -The critical path (or paths) is the longest path (in time) from Start to Finish; it indicates the minimum time necessary to complete the entire project.

Detailed explanation-3: -The critical path is the path through the network that results in the latest completion date of the project. If any activity on the critical path is delayed, the completion of the project will be delayed by an equal amount. It is the path with the greatest total duration.

Detailed explanation-4: -The critical path affects the projects finish date because it is the longest path for completing the tasks and activities within the project. Therefore, any tasks that is delayed on the critical path will delay the whole project and could prevent the project from completing by its deadline.

Detailed explanation-5: -In project management, the critical path is the longest sequence of tasks that must be completed to complete a project. The tasks on the critical path are called critical activities because if they’re delayed, the whole project completion will be delayed.