ENTREPRENEURSHIP

ENTREPRENEURIAL OPERATIONS

TIME MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following documents is most useful when planning out a whole project?
A
Diary
B
To-do list
C
Timeline
D
Gantt chart
Explanation: 

Detailed explanation-1: -Gantt charts can help you visualize what you need to do and how long each task will take, as well as provide a visual of the overall timeline and deadlines. Gantt charts are most effective when you use them as a visual representation of all tasks that you need to complete in order for the overall project to succeed.

Detailed explanation-2: -DUE DATES: The dates are one of the most essential aspects of a Gantt chart since they show project managers not only when the project will start and end, but also when each job will take place. These are shown at the top of the graph.

Detailed explanation-3: -With Gantt charts, project managers can schedule projects, allocate resources, set cost and scope baselines, and identify the critical path.

Detailed explanation-4: -Tasks, their duration, status, and priority. Start and end dates. Progress. Timeline with the time scale. Milestones. Dependencies between tasks. Deadlines. Critical path. 25-Oct-2022

There is 1 question to complete.