BONUS:Your company has been tasked with providing estimates for a road construction project. You have data available related to costs per square feet. You now need to provide an estimate of the cost of the project based on this data what estimation technique is most applicable in such a scenario?
A
Top Down estimates
B
Parametric Estimating technique
C
Bottom Up Estimating
D
Analogous Estimation
Explanation: 

Detailed explanation-1: -The sponsor provides funding directly or indirectly and is responsible for approving or denying the budget. The project sponsor is also generally the one who approves the Project Charter, but that is not mentioned in the question. So the correct answer is Option c.

Detailed explanation-2: -Which of the following best describes the assumptions made by Herzberg’s Hygiene theory? d. Job content factors have no influence in keeping people happy on the job and motivated. The answer is option c-Job content factors have no influence in keeping people happy on the job and motivated.

There is 1 question to complete.