The project manager is looking at the project’s resource needs and lessons learned from past projects. This information causes the project manager to be concerned about the ability to acquire enough resources for the project in six months. Which of the following would be the least effective preventive action?
A
Make sure functional managers have a copy of the resource histogram
B
Show the sponsor the data, and explain the project manager’s concern
C
Determine metrics to use as an early warning sign that resources will not be available
D
Ask functional managers for their opinions
Explanation: 

Detailed explanation-1: -Project Resource Management includes the processes to identify, acquire, and manage the resources needed for the successful completion of the project. To proceed with a project, it is very important to clearly identify and define the type and amount of resources required.

Detailed explanation-2: -7. What conflict resolution technique is a project manager using when he says, “I cannot deal with this issue now!” Delaying the issue is called withdrawal. 8.