What does a resource histogram show that a responsibility assignment matrix does not?
A
Time
B
Activity
C
Interrelationships
D
The person in charge of each activity
Explanation: 

Detailed explanation-1: -What does a resource histogram show that a responsibility assignment matrix does not? A: The responsibility assignment matrix maps specific resources to the work packages from the WBS. On a resource histogram, the use of resources is shown individually or by groups over time.

Detailed explanation-2: -A Responsibility Assignment Matrix (RAM) describes the participation of various organizations, people, and their roles in completing tasks or deliverables for a project. It’s used by the Program Manager (PM) in clarifying roles and responsibilities in a cross-functional team, projects, and processes.

Detailed explanation-3: -A responsibility assignment matrix (RAM) in project management, also known as a RACI chart or RACI matrix, details all the necessary stakeholders and clarifies responsibilities amongst cross-functional teams and their involvement level in a project.

Detailed explanation-4: -This matrix clearly identifies which role each team member has agreed to take on for each of the project’s main deliverables. With these assignments, you can eliminate miscommunication about who’s doing what – and you can help to ensure that your project is successful.