Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
You have just been assigned as project manager for a large telecommunications project. This one-year project is about halfway done. The project team consists of 5 sellers and 20 of your company’s employees. You want to understand who is responsible for doing what on the project. Where would you find such information?
A
Responsibility assignment matrix
B
Resource histogram
C
Bar chart
D
Project organization chart
Explanation: 

Detailed explanation-1: -5. Which of the following sources of power would likely cause a project resource to be committed to the effort? Referent power is the only of the choices to likely get commitment as it focuses on the resource having goodwill towards the PM because of who the PM knows or is associated with.

Detailed explanation-2: -Which of the following conflict resolution techniques will generate the MOST last solution? D: Problem solving (also referred to as collaborating) normally takes more time, but it gets buy-in from everyone, generating a more lasting solution.

There is 1 question to complete.