Which of the following describes a ‘dependency’ within a digital and social media strategy?
A
A reference point that marks a major event in a project
B
Relationships of the preceding tasks to the succeeding tasks
C
Project requirement needing to be completed within a time
D
Formal document to guide and control the use of a strategy
Explanation: 

Detailed explanation-1: -The four main types of activity dependencies include Finish-to-Start (FS), Start-to-Start (SS), Start-to-Finish (SF), and Finish-to-Finish (FF). The following briefly describes these relationship types: Finish-to-Start (FS): The successor activity cannot start unless the predecessor activity finishes.

Detailed explanation-2: -Dependencies are the relationships of the preceding tasks to the succeeding tasks. Tasks may have multiple preceding tasks and multiple succeeding tasks. The most common dependency relationship is a finish-to-start relationship. Task P (predecessor) must be finished before task S (successor) can start.

Detailed explanation-3: -What are dependencies in project management? Every project has dependencies, which Max Wideman’s Glossary defines as the “relationships between products or tasks”, i.e. tasks that require input from other tasks to be completed, or activities that can’t start until a previous activity is done.