Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
The outputs from the Monitor Risks process include all of the following EXCEPT:
|
Project documents updates.
|
|
Work breakdown structure (WBS).
|
|
Change requests.
|
|
Project management plan updates.
|
Explanation:
Detailed explanation-1: -More specifically: “Monitor Risks is the process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project.”
Detailed explanation-2: -Residual risks, fallback plans, and contingency reserves are all outputs of the Plan Risk Responses process, making this the correct answer.
Detailed explanation-3: -For example, the risk breakdown structure pictured above organizes the project’s risks into four major categories: technical, external, organizational, and project management.