A company budgeted 1 hrs of work at €22 per hour for producing one product. The production report shows the following realized numbers:· Numbers of products produced:22, 000· Total labor hours:12, 000· Total labor costs:€240, 000The labor price variance is
|
22, 000 positive
|
|
22, 000 negative
|
|
24, 000 positive
|
|
24, 000 negative
|
Explanation: