If 4 labourers can finish a job in 6 days, how long will it take 3 men to do the job?
A
2 days
B
41/2 days
C
8 days
D
10 days
Explanation: 

Detailed explanation-1: -∴ The number of men needed to be employed to complete the job in 5 days is 63.

Detailed explanation-2: -Answer: The workers needed to complete the job in 4 hours are 12.

Detailed explanation-3: -With the help of C, they were able to complete the work in 6 days.

Detailed explanation-4: -Example 2: What is the efficiency of a person who finishes his job in 5 days? Therefore we can say that he does 1/5th of the work per day. This when we convert it into percentage = 100/5 = 20%. Therefore, his efficiency is 20%.