____ is used to accomplish the project economically in the minimum available time with limited resources
A
Project Scheduling.
B
Network Analysis.
C
Budget Analysis.
D
Critical Planning.
Explanation: 

Detailed explanation-1: -Explanation: Network planning helps in planning, scheduling and controlling, in order to complete the project economically in minimum available time with limited available resources.