Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
Earliest Start Time.
|
|
Event Start Time.
|
|
Effective Start Time.
|
|
Essential Start Time.
|
Detailed explanation-1: -1. Earliest start time (EST): It is the earliest possible time at which an activity can be started.
Detailed explanation-2: -Earliest start time (ES): It is defined as the earliest possible time at which an activity can start. It is calculated by moving from first to last event in a network diagram.
Detailed explanation-3: -Early start time denotes the earliest possible point at which an activity may be commenced. The ES for the first task(s) in a project is set to zero.
Detailed explanation-4: -Early Start Time: The earliest point in the schedule at which a task can begin. Early Finish Time: The earliest point in the schedule at which a task can finish. Latest Start Time: The latest point in the schedule at which a task can start without causing a delay.