Which of the following is not considered to be a characteristic of a project?
|
An established objective
|
|
Complex tasks
|
|
A clear beginning and end
|
|
Only for internal use
|
Explanation:
Detailed explanation-1: -Which of the following is NOT a characteristic of a project? Constrained by limited resources Planned, executed, monitored, and controlled Creates a unique product or service Ongoing and repetitive Answer: D Explanation: A project is a temporary endeavor undertaken to create a unique product, service, or result.
Detailed explanation-2: -Temparary nature is not a project.
Detailed explanation-3: -Six Characteristics of a Project A project is typically for a customer. The project is temporary in nature. It typically has a defined start and a defined end-point. The project will have a unique set of requirements that need to be delivered within the boundaries of this project.