Rapid Application Development is used for smaller projects combines the steps of SDLC into five phases.
A
true
B
false
Explanation: 

Detailed explanation-1: -The rapid application development process is different. Instead of lots of detailed planning, you break the project into five phases: business modeling, data modeling, process modeling, application generation, and testing and turnover.

Detailed explanation-2: -However, there is little room for change once a phase is considered complete, as changes can affect the software’s delivery time, cost, and quality. Therefore, the model is most suitable for small software development projects, where tasks are easy to arrange and manage and requirements can be pre-defined accurately.

Detailed explanation-3: -What Are the 7 Phases of SDLC? The new seven phases of SDLC include planning, analysis, design, development, testing, implementation, and maintenance.