BONUS:Your company has been tasked with providing estimates for a road construction project. You have data available related to costs per square feet. You now need to provide an estimate of the cost of the project based on this data what estimation technique is most applicable in such a scenario?
A
Top Down estimates
B
Parametric Estimating technique
C
Bottom Up Estimating
D
Analogous Estimation
Explanation: 

Detailed explanation-1: -A data point in a control chart that requires investigation is called a special cause.