Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
You are a project manager leading a cross-functional project team in a weak matrix environment. None of your project team members report to you functionally, and you do not have the ability to directly reward their performance. The project is difficult, involving tight date constraints and challenging quality standards. Which of the following types of project management power will likely be the MOST effective in this circumstance?
|
Referent
|
|
Expert
|
|
Penalty
|
|
Formal
|
Explanation: