Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Which of the following documents is drafted in the planning stage of project management:
|
Project charter
|
|
Statement of work
|
|
Lessons-learned document
|
|
Work breakdown structure
|
Explanation:
Detailed explanation-1: -Project Plan: The project plan document is divided in sections to cover the following: scope management, quality management, risk assessment, resource management, stakeholder management, schedule management and the change management plan.
Detailed explanation-2: -initiation. planning. execution. monitoring and control. closure.
Detailed explanation-3: -Level 0: Project title or final deliverable. Level 1: Major deliverables. Level 2: Deliverables that can still be broken down. Level 3: Can be assigned to the team to complete the third level deliverables. 28-Jan-2023