A PERT chat’s full name is ____
A
Evaluation and Review Technic for programs
B
Evaluation of program and robotic techniques
C
Assessment of program and robotics
D
Technology for program evaluation and rating.
Explanation: 

Detailed explanation-1: -A program evaluation review technique (PERT) chart is a graphical representation of a project’s timeline that displays all of the individual tasks necessary to complete the project. As a project management tool, the PERT chart is often preferred to the Gantt chart because it identifies task dependencies.

Detailed explanation-2: -A PERT chart is a visual project management tool used to map out and track the tasks and timelines. The name PERT is an acronym for Project (or Program) Evaluation and Review Technique.

Detailed explanation-3: -What is Project Evaluation Review Technique (PERT)? In project management, the Project Evaluation Review Technique, or PERT, is used to identify the time it takes to finish a particular task or activity. It is a system that helps in the proper scheduling and coordination of all tasks throughout a project.