SOFTWARE PROJECT MANAGEMENT
PROJECT SCHEDULING AND TRACKING
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
Make the changes to the baseline documents, then present them to the team in a team meeting so everyone will be up to date on the modifications.
|
|
Make the decision to change the project scope to accommodate the changes.
|
|
Send those changes through the organization’s change control process.
|
|
Consult with your project stakeholders to let them know of the changes that the team will be making.
|
Detailed explanation-1: -Whether you use an agile or traditional lifecycle, you still need to define your change control process. Typically the Product Owner approves the change requests with input from key stakeholders. Change requests that impact active sprints are usually approved for implementation in a subsequent sprint.
Detailed explanation-2: -Understand and communicate the need behind the change. Document the change. Evaluate the change and understand the impact in scope, schedule, and budget. Consider the implications and get any change(s) approved. Implement and communicate to the team.
Detailed explanation-3: -Review the schedule and schedule baseline regularly. Identify variances and take corrective action if needed. Monitor the progress of the project and make necessary adjustments. More items •04-Jan-2023