Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following documents is created as needed in all Project Risk Management processes except the Plan Risk Management process?
A
Risk Breakdown Structure
B
Risk Audit Document
C
Risk Reassessment Document
D
Risk Register
Explanation: 

Detailed explanation-1: -risk register is the adequate document.

Detailed explanation-2: -The 4 essential steps of the Risk Management Process are: Identify the risk. Assess the risk. Treat the risk. Monitor and Report on the risk.