Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
____ are used in six sigma
A
Black belt
B
Green belt
C
Both black and green belt
D
None of the above
Explanation: 

Detailed explanation-1: -Black Belt: Leads problem-solving projects. Trains and coaches project teams. Green Belt: Assists with data collection and analysis for Black Belt projects. Leads Green Belt projects or teams.

Detailed explanation-2: -Black belts have a thorough understanding of all aspects of the define, measure, analyze, improve and control (DMAIC) model in accordance with Six Sigma principles. They have basic knowledge of lean enterprise concepts, are able to identify non-value-added elements and activities and are able to use specific tools.

Detailed explanation-3: -Six Sigma is a process that makes use of statistics and data analysis to analyze and reduce errors or defects. In this process, the purpose is to improve cycle times while reducing manufacturing defects to no more than 3.4 defects per million units or events.