Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following is an important factor that can affect the accuracy and efficacy of estimates?
A
Project size
B
Planning process
C
Project complexity
D
Degree of structural uncertainty
Explanation: 

Detailed explanation-1: -1. Which of the following is an important factor that can affect the accuracy and efficacy of estimates? Explanation: As size increases, the interdependence among various elements of the software grows rapidly.

Detailed explanation-2: -In the context of effort estimation, the term “effort factor” refers to product-, process-, or personnel-related characteristics that have an impact on the development effort. In practice, software size is the most important determinant of development effort and, as such, is always considered.

Detailed explanation-3: -Explanation: LOC or Line of Code is a direct measure to estimate project size.