Which of the following is NOT a goal of a pilot project for tool evaluation?
A
To assess whether the benefits will be achieved at a reasonable cost
B
To evaluate how the tool fits with existing processes and practices
C
To determine use, management, storage and maintenance of the tool and test assets
D
To reduce the defect rate in the pilot project
Explanation: 

Detailed explanation-1: -Which of the following is MOST likely to be used as a reason for using a pilot project to introduce a tool into an organization? The need to evaluate how the tool fits with existing processes and practices and determining what would need to change.

Detailed explanation-2: -Pilot projects test whether or not a process or product will work well in a given environment. It’s considered a feasibility study, where appropriateness is figured out before the new product or process is implemented into the existing operations.