SOFTWARE ENGINEERING

EMERGING TRENDS IN SOFTWARE ENGINEERING

MISCELLANEOUS

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Activity in a network diagram is represented by?
A
Rectangles
B
Arrows
C
Squares
D
Circles
Explanation: 

Detailed explanation-1: -In the precedence diagramming method for creating network diagrams, each box, or node, represents an activity-with the arrows representing relationships between the different activities.

Detailed explanation-2: -In activity on arrow diagrams, arrows are used to show activities. In activity on arrow diagrams, nodes are called events. First node is always the “START” event and last node is the “END” event.

There is 1 question to complete.