Activity in a network diagram is represented by?
|
Rectangles
|
|
Arrows
|
|
Squares
|
|
Circles
|
Explanation:
Detailed explanation-1: -In the precedence diagramming method for creating network diagrams, each box, or node, represents an activity-with the arrows representing relationships between the different activities.
Detailed explanation-2: -In activity on arrow diagrams, arrows are used to show activities. In activity on arrow diagrams, nodes are called events. First node is always the “START” event and last node is the “END” event.