COCOMO model is ____
|
Common Cost estimation model
|
|
Constructive Cost estimation model
|
|
Complete cost estimation model
|
|
Comprehensive cost estimation model
|
Explanation:
Detailed explanation-1: -COCOMO: It is a procedural cost estimate model for software projects and often used as a process of reliably predicting the various parameters associated with making a project such as size, effort, cost, time, and quality.
Detailed explanation-2: -COCOMO stands for Constructive Cost Model. Barry W. Boehm proposed COCOMO, a procedural software cost-estimating methodology, in 1981. This cost estimation technique is widely used to forecast the effort, development time, average team size, and work needed to complete a software project.