Critical path lies along the activities having total float
A
positive
B
negative
C
zero
D
same
Explanation: 

Detailed explanation-1: -Total float is often known as the slack. On a critical path, the total float is zero as the critical path already gives the longest sequence of activities in a project plan which must be completed on time for the project to complete on the due date.

Detailed explanation-2: -Critical activity: Critical activities are those activities that lie on critical path. The float of activities that lie on the critical path is zero.

Detailed explanation-3: -The critical activity has zero float.