Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Critical path lies along the activities having total float
|
positive
|
|
negative
|
|
zero
|
|
same
|
Explanation:
Detailed explanation-1: -Total float is often known as the slack. On a critical path, the total float is zero as the critical path already gives the longest sequence of activities in a project plan which must be completed on time for the project to complete on the due date.
Detailed explanation-2: -Critical activity: Critical activities are those activities that lie on critical path. The float of activities that lie on the critical path is zero.
Detailed explanation-3: -The critical activity has zero float.