During which phase of the SDLC are users trained to use the new system?
A
preliminary investigation
B
systems implementation
C
systems development
D
systems maintenance
Explanation: 

Detailed explanation-1: -System performance is compared to performance objectives established during the planning phase. Implementation includes user notification, user training, installation of hardware, installation of software onto production computers, and integration of the system into daily work processes.

Detailed explanation-2: -New or alternative systems are designed during the systems development phase of the SDLC.

Detailed explanation-3: -1) This phase of the SDLC is known as the “ongoing phase” where the system is periodically evaluated and updated as needed.